Our Projects

We conduct project to make our services more reliable to our clients and also making the access of water to all parts of the Coast Region.

Our World Bank Projects

Water for Schools World Bank Projects

Main Contract Names                             Contract Scope                                      Status                          
Various-8 Boreholes
-100m3 Djabias
-Roof Rainwater Harvesting
-Water Tanks
  • Some Equalization Fund Projects stalled due to price escalations. The Agency is looking at alternative ways of completing the contracts.
  • Small dams and pans - CWWDA received only Kes 44m out of the required Kes 175m. Twenty (20) projects have been completed, Eight projects are still outstanding
  • Water for schools successfully completed.
  • Cross County Water Projects- successfully completed

Dongo Kundu Project- Phase 2 World Bank Projects

Main Contract Names                        Contract Scope                                                              Status       
-4.2Km of 700mm diameter pipeline
-Acquisition of Land for tank site
-Signed Contract Kshs. 226m

-Physical progress is 40%
-Stalled
- New procurement

  • Phase II of the works - Construction of 2.5km of pipeline; Works Stalled – with progress at 40%, due lack of budgetary allocations and pipe/material price escalations making the Contractor to face serious challenges in procurement of steel pipes, lack of site for tank and challenges with new bypass road crossings

Water and Sanitation Development Project (WSDP) World Bank Projects

Main Contract NamesContract ScopeStatus
Baricho Replacement Boreholes-Boreholes 1,3 & 4
-Drilling & Equipping
-Local Protection Works
-Completed 
Mombasa North Mainland Lot 1A-Water Distribution Network (88 km)-Contract signed on 23rd March 2021
-90% physical progress/211% of elapsed time
North Mainland Nyali Phase 1-Water Distribution Network (65 km)-Contract signed on 23rd March 2021
-90% physical progress/211% of elapsed time
Baricho Protection Works-Gabion Works
-4km of Piling Works
-8,950 m2 of Access Road
-Completed and on DLP
Second Baricho Kakuyuni Line-29 km of 800mm pipeline
-5,000 m3 tank at Kakuyuni
-3 pump sets &  Electromechanical works
-Completed and on DLP

Taita Taveta University Borehole World Bank Projects

Drilling and equipping 1no borehole, pipe extension and plastic storage tank to serve Mwamsha water supply and Taita Taveta University

County: Taita Taveta                              Project Cost: 9.5 M

Construction of Small Earth Dams and Water Pans under National Water Harvesting and Storage Programme Phase II World Bank Projects

Setting out of the dam and ancillary works, earthworks excavations and filling, compaction of fill layers to 85% MDD, shaping dam embankments, construction of water intake infrastructure and cattle troughs and testing and commissioning of works.

Counties: Kwale, Kilifi                                                  Project Cost: 127.7M

Nyalani Water Supply Project (Kwale County) World Bank Projects

19km Rising main line 110/225 uPVC, 225m3 masonry tank, 5No. Water kiosks with 10m3 storage tanks, Pump house, 2No low pumping sets, and 2No. High lift, pumps, treatment set

County: Kwale               Project Cost: 88.4M