Our Projects

We conduct project to make our services more reliable to our clients and also making the access of water to all parts of the Coast Region.

Our adb Projects

CWWDA HQs Office Construction

Main Contract Names                          Contract Scope                                  Status                                 
CWWDA HQs Office Construction 

-Main Block 2,150sq. m
-Services

  • Construction of a Four-storey office space with surface level parking,
  • Supply, Installation, Testing and Commissioning of Electrical Installations Works
  • Supply, Installation, and Testing and Commissioning of of plumbing, drainage, firefighting and LPG installation Works
  • Supply, Installation, and Testing and Commissioning of the air conditioning and mechanical ventilation
  • Construction of a Four-storey office space with surface level parking,
  • Supply, Installation, Testing and Commissioning of Electrical Installations Works
  • Supply, Installation, and Testing and Commissioning of of plumbing, drainage, firefighting and LPG installation Works 
  • Supply, Installation, and Testing and Commissioning of the air conditioning and mechanical ventilation 

-Studies completed
-tender documents completed
-Ready for financing by ADBDesigns and tender document completed

  • NEMA License acquired
  • Awaiting budgetary allocation for the commencement of the procurement process

Kenya Towns Sustainable Water Supply and Sanitation Program

Main Contract NamesContract ScopeStatus
Pemba Dam Rehabilitation

Construction of New WTP .Rehabilitation of the Weir Interconnection of the existing system.
Improve supply by adding 3000m3 per day to Kwale, Kinango, Likoni and Mombasa via Changamwe.

  • Rehabilitation of Dam/weir and spillway 
  • Installation of new raw water intake
  • Installation of new raw water pumping station and rising main
  • Construction of new conventional water treatment plant of 3,000m3/day capacity
  • Construction of new houses for Operators
  • Construction of operation/ lab and chemical stores

100%

  • Site Handover – 15th Nov 2018
  • Commencement – 15th Jan 2019
  • Original Completion date – 15th July 2020
  • Contract price was Kshs. 286,801,675
  • Cumulative payments Kshs. 266,359,226.50
  • Status: – 100% Complete. 
  • Contractor: M/s Zhongao Overseas Construction Engineering Company ltd
Changamwe Repooling

-9.8km of sewers
-260 Man holes

  • Rehabilitation of approx. 800m of trunk mains
  • Rehabilitation of approx. 9km secondary sewer network
  • Extension of secondary sewer network
  • Construction of approx. 260 No. manholes

-25% 
-Court Injunction by the contractor
-Arbitration ongoing

  • Commencement – 26th Aug 2020
  • Key challenge – contract terminated due to non-performance
  • Case was in Court and now in arbitration
  • Contract price was Kshs. 204,483,295
  • Cumulative payments Kshs.71,816,260.95
  • Contractor: M/s Njuca Construction ltd
Watamu Water Distribution Network Works 

-100%
-DLP ongoing    

  • Commencement – 21st October 2025
  • Original Completion date – 22nd October 2026
  • Contract price is Kshs. 40,965,140.16
  • Cumulative payments Kshs. 0
  • Status– ongoing at 90%