Our Projects

We conduct project to make our services more reliable to our clients and also making the access of water to all parts of the Coast Region.

Our Ongoing Projects

Equalization funds project

Construction of Pipelines upto 100km (63-150 dia UpVC)  Drilling and Equipping of Boreholes, Construction of earth dams increasing storage in rural areas by 200,000m3, Construction of storage tanks increased storage of safe water by 4000m,  Construction of sea walls    

Counties: Kilifi, Kwale, Tana River, Taita -Taveta, Lamu        Project Cost: 1.86 B           Period: 2017-2019

Immediate Baricho Works Expansion & New Pipelines to Kilifi & Gongoni (Lot 3)

Construction of DN 500 Kakuyuni-Kilifi pipeline (56km) and DN 400 Kakuyuni-Gongoni Pipeline (37km).

County: Kilifi                          Project Cost: 2.4 B                                       Period: 2016-2019

Our Past Projects

Baricho Immediate Works with the following Lots: Augmentation of the Baricho Well field & Electromechanical Work.

Drilling and equipping 3No boreholes 220,000m3/day, Electromechanical works, 2.5 Km DN600 collector rising main.

County: Kilifi                     Project Cost: 590M          Period: 2015-2018

Drought Mitigation (Kizingitini Water Supply Project)

Developing and Equipping 2No. Shallow wells, Constructing 25m3 and 50m3 masonry tanks, Installing a desalination unit, Laying pipe lines, Supplying and installing a Gen. Set, Constructing an elevated structure to accommodate 10m3 tank, construction of a grade 9 house and constructing Perimeter fence.

County: Lamu                                                         Project Cost: 19M

Lamu Port Immediate Water Supply Project

Drilling of 2No. boreholes at Hindi (Bele-bele), Equipping of 3No. Boreholes, Installing an overhead power Supply 3-phase 3km long, Constructing 1No. 4m by 6m Pump House, Procure and Install 1 No. 62 KW,Generating Set, Constructing 1No. Double Grade 9 staff House Type A1, Fabrication and Installation of 120 m3 Steel elevated tank on a 17 m at Belele site, Purchase and laying of diameter 160mm uPVC Class C length 5.179km and diameter 90mm uPVC Class Clength1.4km as rising main / Gravity Main.

County: Lamu                                                        Project Cost: 50M

Installation of 222No. 10m3 capacity plastic tanks in Coast Water Services Board Area. (Lot 1) Installation of 222No. 10m3 capacity plastic tanks in Coast Water Services Board Area. (Lot 1) Installation of 222No. 10m3 capacity plastic tanks in Coast Water Services Board Area. (Lot1)

Provision of gutters, base slab materials and all fittings, construct a base slab for the plastic tanks and gutters, installation of the plastic tanks and gutters.

Counties: All Counties (except Mombasa)                          Project Cost: 102.8M

UNICEF

Shallow wells drilling Excavating and Equipping, borehole drilling and Equipping, management trainings, operation trainings.

Counties: Kwale, Tana River                           Project Cost: 4.M

Unicef Wash Emergency

Shallow wells equipping

County: Kilifi                                    Project Cost: 0.5M 

Malukiloriti in (Mahoo Ward)-Water Distribution

Increase water supply by 1000m3/day; pipeline, genset, power house tank, submersible pump and Community water points 4no s. This project will  serve 5000 people.

County: Taita Taveta                                          Project Cost: 8.6M

Taita Taveta University Borehole

Drilling and equipping 1no borehole, pipe extension and plastic storage tank to serve Mwamsha water supply and Taita Taveta University

County: Taita Taveta                              Project Cost: 9.5 M

Mbololo Water Project

Pipeline extension from Mbololo water project, 20no ½ “diameter Water meters, to serve approx. 2,500 people

County: Taita Taveta                         Project Cost: 8.1M

Manga –Mlilo- Kishushe water Project

Pipeline construction, 500m3; 220m3 Pump House and kiosks construction (Phase under construction and 90% complete)

County: Taita Taveta                                          Project Cost: 53M

Mwakitau water supply

Bore hole drilling, equipping, storage tanks construction and GI pipeline for Raising main.

County: Taita Taveta                          

Kengwa water supply

Intake design and improvement

County: Taita Taveta                               Project Cost: 0.5M

Mwasima Nuru water supply

Replacement of 2.5” ØGI pipelineReplacement of 2.5” ØGI pipeline.

County: Taita Taveta                                        Project Cost: 2M

Mrugua Water Supply

100M3 MASONRY Storage Tank, Various Ø sizes of G.I Pipeline rehabilitation and extension.

County: Taita Taveta                                        Project Cost: 2.5M

Hola WSP Reticulation Improvement project

3.5m diameter pontoon, 2 submersible pumps on pontoon (Q=80m3/h, H=19m), 2 high lift pumps, 1.35km DN200 steel raw water main, Rehabilitation of treatment works 12000m3/day, 500 m3 elevated tank, 1.01km DN63, 1.45km DN90, and 10,143 consumer meter 15mm dia.

County: Tana River                                          Project Cost: 100.4M

Construction of Surface Modular Pressed Steel Tanks

Surface modular of Capacity of 500m3 made of Pressed Steel.

Counties: Tana-River, Kwale, Kilifi, Taita Taveta    Project Cost: 79.2M

Elevated steel tanks at 15No Borehole sites in CWSB Region

Construction of 15 No. 100m3 -15m high elevated steel tanks at 15No Borehole sites in CWSB Region

Counties: Tana-River, Kwale, Kilifi, Taita Taveta              Project Cost: 64M                            

Mombasa West Mainland Sewerage Rehabilitation

Rehabilitation of 619 manholes, 1.21km sewer line, Kipevu treatment plant, and 4 pumping stations

County: Mombasa                         Project Cost: 211.7M

Mombasa West Mainland Sewerage Rehabilitation

Rehabilitation of 619 manholes, 1.21km sewer line, Kipevu treatment plant, and 4 pumping stations.

County: Mombasa                                     Project Cost: 211.6M

Construction of Small Earth Dams and Water Pans under National Water Harvesting and Storage Programme Phase II

Setting out of the dam and ancillary works, earthworks excavations and filling, compaction of fill layers to 85% MDD, shaping dam embankments, construction of water intake infrastructure and cattle troughs and testing and commissioning of works.

Counties: Kwale, Kilifi                                                  Project Cost: 127.7M

Drought Response Programme

Development of water sources by equipping of existing boreholes with submersible pumps and solar system, drilling of five new boreholes and equipping and commissioning, construction of five modular steel tanks 500m3, construction of fifteen elevated steel tanks 100m3, Installation of 200No. 10m3 plastic storage tanks with gutters in various public institutions. 

Counties: Taita Taveta, Kilifi, Kwale, Lamu Tana-River               Project Cost: 250 M

Extension of Water and Sanitation Services to Informal Settlements In Mombasa Lot 2-Matopeni, Shauri Yako, Kisumu Ndogo and Maweni

Construction of 8km pipeline of ranging from 90mm-40mm dia, construction of seven (7) ablution blocks in the project area to improve the sanitation, connection of about No. 380 houses to the new system, construction of 20-yard taps to serve the wider community.

County: Mombasa                         Project Cost: 149 M

Extension of Water and Sanitation Services to Informal Settlements In Mombasa [Lot 1: Ziwa La Ngombe And V.O.K, Mombasa]

Construction of 7.5km pipeline of ranging from 250mm-50mm with another additional 4km, construction of an office block in Kisauni yard, construction of two ablution blocks in Bombolulu and Ziwa la Ng’ombe, connection of about 190 houses to the new system, construction of 10-yard taps.

County: Mombasa                                    Project Cost: 129M

Rehabilitation / Extension of Mombasa Water Supply Works – Lot 1

Replacement of distribution lines and 40.23km of trunk mains, diameters 160mm to 700mm. Ancillary works, water works, bulk meters, rehabilitation of storage tanks, supply of sewer maintenance equipment’s.

County: Mombasa                                     Project Cost: 990M

Rehabilitation / Extension of Mombasa Water Supply Works – Lot 2

Lay 43Km pipeline within North mainland (Shanzu, Nguu tatu, Mishomoroni and Nyali near Nakumatt), Island (Tudor), West Mainland (Mikindani), South mainland (Likoni) and appurtenances.

County: Mombasa                                           Project Cost: 1.0B

Malindi Informal settlement Lot 1: Kisumu Ndogo.

Construction of 14km new pipeline, Construction of new ease treat ablution block in HGM primary, office block for malindi WSP, rehabilitation of a pour flush toilet, 190 connections, 10 Yard taps.

County: Kilifi                                             Project Cost: 103.7M

Malindi Informal settlement Lot 2: Kibokoni.

12Km uPVC PN16, Diameter 63mm to 160mm, Construction of ablution block at Kibokoni Secondary. 190 individual connections, Ten-yard taps and one kiosk

County: Kilifi                                            Project Cost: 75M

Tiwi Boreholes Rehabilitation Project

Construction of 17km new pipeline, Drill 7 new bore holes, electro-Mechanical works for 11 bore holes. Rehabilitation of 3 bore holes.

Counties: Kwale, Mombasa.                                 Project Cost: 248.2M

Rehabilitation of Mzima I Pipeline

Replace 26km DN700 steel pipeline, Rehabilitation of 3 river crossings, Replace 220 air valves DN100, Repair 9 BPTs, Repair of 30km pipeline access road, Repair of guest houses at head-works, By-pass BPT 1 with 2.9km DN800 steel pipe, Rehab of Mazeras reservoirs, Construction of repair kit shed/store at Mazeras.

County: Taita Taveta                                      Project Cost: 1.1B

Baricho Water Works Rehabilitation project

Development of 8 wells, replacement of 13 pumps, replacement of 6 transformers, replacement of 21 valves, replacement of 11 power poles

County: Kilifi                                         Project Cost: 1.3B

KIDDP Mariakani-Kaloleni Water supply Improvement project

225m3 sump, one number pump house, supply and installation of two number duty pumps and two number standby pumping units for Mariakani and Kaloleni. 3 Phase power connection, 18.1Km uPVC dia 90-200mm

County: Kilifi                                            Project Cost: 90M

Kwale WSP Reticulation Improvement project

Rehabilitation of 2 pumps, 2 switch gear, construction 18.967km pipe line, and 2 Bulk meters.

County: Kwale                                   Project Cost: 172.3M

Mkanda Phase I and II

Treatment plants, Rising Main, pumping units. Rehabilitation of Raw Water Pumping Station & Pipeline, Rehabilitation of Treatment Works, augmentation of Raw Water main and Laying Gravity main, Rehabilitation of Kibuyuni-Magwashenyi Pipeline.

County: Kwale                                  Project Cost: 200M

National Rain Water Harvesting (NRWHP) 12 Dams.

Construction of 20,000m3 capacity water pans and earth dams.

Counties: Kwale, Taita Taveta, Kilifi, Tana River  Project Cost: 116M

Nyalani Water Supply Project (Kwale County)

19km Rising main line 110/225 uPVC, 225m3 masonry tank, 5No. Water kiosks with 10m3 storage tanks, Pump house, 2No low pumping sets, and 2No. High lift, pumps, treatment set

County: Kwale               Project Cost: 88.4M

Kilifi WSP Reticulation Improvement project

Rehabilitation of 35.1km pipeline, construction of new 500m3 tank and install new valves

County: Kilifi                    Project Cost: 204.5M

Malindi WSP Reticulation Improvement

Construction of 17 Km pipeline DN 350mm

County: Kilifi                                     Project Cost: 218.1M

Lamu WSP Reticulation Improvement project

Construction of 4 wells, 7.25km, 11kv overhead electricity line, 7 transformers 11/0.415Kv, remote control panel for 9 wells, install 39 no. Submersible pumps. 20 Monitoring data loggers, 38.48km pipeline, 225m3 masonry tank. 700 consumer meters, 1250m3 tank

County: Lamu                                     Project Cost: 288.4M

Lamu Port Immediate Water Supply Project

Drilling of 2No. boreholes at Hindi (Belebele), Equipping of 3No. Boreholes, Installing an overhead power supply 3-phase 3km long, Constructing 1No. 4m by 6m Pump House, Procure and Install 1 No. 62 KW Generating Set, Constructing 1No. Double Grade 9 staff House Type A1, Fabrication and Installation of 120 m3 Steel elevated tank on a 17 m at Belele site, Purchase and laying of diameter 160mm uPVC Class C length 5.179km and diameter 90mm uPVC Class Clength1.4km as rising main / Gravity Main.

County: Lamu                          Project Cost: 50M

Voi WSP Reticulation Improvement

Rehabilitation of pumps and switch gear, installation of stand by pumps at Maungu and Itinyi, construction of 10.8km pipeline works, 500m3 town reservoir, 100m3 tank at Bomani, protection of tanks and pipeline from erosion and installation of bulk meters.

County: Taita Taveta                      Project Cost: 137.6M

Augmentation of Taveta Lumi W/Supply in Taita Taveta County

2No low and high lift pumps, Replacement of Chlorine doser and repair of 50m long 150mm raw water main. 5.6km 250 Epoxy coated steel rising main. Repair of 200m3 existing chlorination tank and elevated steel tank.

County: Taita Taveta                                Project Cost: 85.6M

Marere Pipeline Replacement

Improvement of Votia and Mwalughaje intake works, Improvement of treatment at Head works, Extension of power line to head works, replacement of 56km of pipeline and appurtenances, Construction of Kaya Bombo reservoir 1140m3.

County: Kwale, Mombasa.                  Project Cost: 1.3B

Our Proposed Projects

Drilling and Equipment of the three (3) Replacement Boreholes in Baricho Wellfield

Replace the damaged boreholes and increase supply by 15,000m3 per-day.
Improve supply to 200,000 people in Malindi, Kilifi, Mtwapa and Mombasa.

Project Status: Tender document under preparation for Design development.

Funded by: GoK/World Bank             Counties: Kilifi                      Project Cost: 400M

Garsen-Lamu water supply scheme, 600 mm, 110 km long

Construction of 110km pipeline diameter 600mm.
The project will supply drinking water to the residents of Lamu, Tana-River. This project will serve approximately 900,000 people

Project Status: Negotiation of financing agreement ongoing

Funded by: PPP                   Counties: Tana-River, Lamu              Project Cost: 18B

Lappset Desalination (SWRO)

Increase water supply to Lamu Port by 3000m3 per day.
Safe drinking water to port users and ships.

Project Status: Awaiting for funds from Ministry of Water and Sanitation.

Funded by: GoK                               Counties: Lamu                         Project Cost: 600M

Changamwe Repooling sewers rehabilitation

Rehabilitation of WWTP,Construction of Secondary Sewers, Interconnections
Increase access to sewerage surfaces to Changamwe residents.

Project Status: Procurement of the contractor ongoing

Funded by: ADB                                   County: Mombasa           Project Cost: 500M

Pemba Dam water supply

Construction of New WTP .Rehabilitation of the Weir Interconnection of the existing system.
Improve supply by adding 3000m3 per day to Kwale, Kinango, Likoni and Mombasa via Changamwe.

Project Status: Procurement of the contractor ongoing.

Funded by: ADB                        County: Kwale             Project Cost: 500M        

Baricho 2 expansion Supply Systems Works

Drilling of high yield boreholes and construction of collector rising main.
Increase water supply by 80,000m3 per day to serve about 1,800,000 people.

Project Status: Sourcing for funds.

County: Kilifi                                                Project Cost: Kilifi

Voi-Wundanyi Pipeline: Off take from Mzima II

Expansion of the intake tunnel, Construction of 220km of DN 1,200 pipeline, construction of reservoirs.
The project will supply drinking water to the residents of Taita Taveta, Kwale, Kilifi and Mombasa Counties. This project will serve approximately 900,000 people

Project Status: Negotiation of financing agreement ongoing          

Funded by: GoK is sourcing for financier of the project, China Exim        County: Taita-Taveta              Project Cost: 2B

Mzima II

Expansion of the intake tunnel, Construction of 220km of DN 1,200 pipeline, construction of reservoirs.
The project will supply drinking water to the residents of Taita Taveta, Kwale, Kilifi and Mombasa Counties. This project will serve approximately 900,000 people

Project Status: Negotiation of financing agreement ongoing between National Treasury and China Exim banks.

Funded by: GoK is sourcing for financier of the project,China Exim.  Counties: Taita-Taveta,Kwale,Kilifi,Mombasa           Project Cost: 35B

Mwache Dam Treatment Plant

The project is designed to increase the water supply into the systems by 186,000m3/day.
This project will transform the social wellbeing of Kenyans by making water available to them and will serve up to 1,500,000 people. The target areas are Mombasa county and some parts of Kwale County

Project Status: Procurement of Design and Supervision Consultant ongoing.

Funded by: AfD/World Bank                County: Kwale               Project Cost: 6.5B

Mwache Dam Transmission Lines

The project is designed to increase the water supply into the systems by 186,000m3/day.
This project will transform the social wellbeing of Kenyans by making water available to them and will serve up to 1,500,000 people. The target areas are Mombasa county and some parts of Kwale County.

Project Status: Procurement of Design and Supervision Consultant ongoing.

Funded by: AfD/World Bank          Counties: Mombasa, Kwale           Funded by: AfD/World Bank

 

Construction of Mwache dam

The project is designed to increase the water supply into the systems by 186,000m3/day.
This project will transform the social wellbeing of Kenyans by making water available to them and will serve up to 1,500,000 people. The target areas are Mombasa county and some parts of Kwale County.

Project Status: Consultants for Design Review and Construction Supervision for the Dam were recruited, Shortlist of Contractors completed and sourcing for proposals ongoing.

Funded by: GoK, World Bank, AfD              County: Kwale                   Project Cost: 20B