Our Projects

We conduct project to make our services more reliable to our clients and also making the access of water to all parts of the Coast Region.

Our Ongoing Projects

CWWDA HQs Office Construction

Main Contract Names                          Contract Scope                                  Status                                 
CWWDA HQs Office Construction -Main Block 2,150sq. m
-Services
-Studies completed
-tender documents completed
-Ready for financing by ADB

Makamini Dam Phase 1 ( D&B) GOK Projects

Main Contract Names                           Contract Scope                                     Status                             
Makamini Dam Phase 1 ( D&B)-9m high dam, 740m length earth dam with spillway
-WTP capacity 2,815m3/d
-Rising Main 225 dia and 700m long
-Water Tanks 3,000m3
-Detailed Design studies completed
-65% physical progress/Elapsed time 127%
-Works stalled due to RAP

Dongo Kundu Project- Phase 2 GOK Projects

Main Contract Names                        Contract Scope                                                              Status       
-4.2Km of 700mm diameter pipeline
-Acquisition of Land for tank site
-Signed Contract Kshs. 226m-Physical progress is 40%
-Stalled
- New procurement

Kenya Towns Sustainable Water Supply and Sanitation Program

Main Contract NamesContract ScopeStatus
Pemba Dam RehabilitationConstruction of New WTP .Rehabilitation of the Weir Interconnection of the existing system.
Improve supply by adding 3000m3 per day to Kwale, Kinango, Likoni and Mombasa via Changamwe.
100%
Changamwe Repooling-9.8km of sewers
-260 Man holes
-25% 
-Court Injunction by the contractor
-Arbitration ongoing
Watamu Water Distribution Network Works -100%
-DLP ongoing          
 

Improvement of Drinking Water and Sanitation Systems in Mombasa AFD Projects

Main Contract NamesContract ScopeStatus
Mwache WTP-Raw water pumping station
-186,000 m3/d WTP
-Clear Water Tanks
-Preliminary Design Studies Completed
-NOL for Prequalification Docs obtained
-Bidding ongoing
Mwache SML Transmission Line and Terminal Tank-28 km of Transmission line
- 28,000 m3 Tank at Dongo Kundu
-Draft Detailed Design Completed
-NOL for prequalification Docs obtained
-Bidding ongoing
Mwache WML Transmission Line and Terminal Tanks-12 km of Transmission line
- 14,000 m3 Tank at Bonje & 16,000 m3 Changamwe Birikani
-Draft Detailed Design Completed
-Draft Prequalification Docs Completed
Mwache NML Transmission Line and Terminal Tank-22 km of Transmission line
- 14,000 m3 Tank at Nguu Tatu
-Draft Detailed Design Completed
-Draft Prequalification Docs Completed
SML & WML Distribution Network-Water Distribution Network (66 km)-Bids docs submitted submitted on 10th Jan  23 
-Tender Cancelled
NRW Works (MOWASCO)DMAs ImplementationProcurement of Consultant ongoing at Draft Contract
Likoni Emergency Works -Works contract singed on 15th August 2021
-Master List tax exemption Approved
-Vehicles, pipes and casing specific exemption obtained
-52% physical progress/183% of elapsed time

Water and Sanitation Development Project (WSDP) World Bank Projects

Main Contract NamesContract ScopeStatus
Baricho Replacement Boreholes-Boreholes 1,3 & 4
-Drilling & Equipping
-Local Protection Works
-Completed 
Mombasa North Mainland Lot 1A-Water Distribution Network (88 km)-Contract signed on 23rd March 2021
-90% physical progress/211% of elapsed time
North Mainland Nyali Phase 1-Water Distribution Network (65 km)-Contract signed on 23rd March 2021
-90% physical progress/211% of elapsed time
Baricho Protection Works-Gabion Works
-4km of Piling Works
-8,950 m2 of Access Road
-Completed and on DLP
Second Baricho Kakuyuni Line-29 km of 800mm pipeline
-5,000 m3 tank at Kakuyuni
-3 pump sets &  Electromechanical works
-Completed and on DLP