We conduct project to make our services more reliable to our clients and also making the access of water to all parts of the Coast Region.
Our Ongoing Projects
CWWDA HQs Office Construction
Main Contract Names
Contract Scope
Status
CWWDA HQs Office Construction
-Main Block 2,150sq. m -Services
-Studies completed -tender documents completed -Ready for financing by ADB
Makamini Dam Phase 1 ( D&B)GOK Projects
Main Contract Names
Contract Scope
Status
Makamini Dam Phase 1 ( D&B)
-9m high dam, 740m length earth dam with spillway -WTP capacity 2,815m3/d -Rising Main 225 dia and 700m long -Water Tanks 3,000m3
-Detailed Design studies completed -65% physical progress/Elapsed time 127% -Works stalled due to RAP
Dongo Kundu Project- Phase 2GOK Projects
Main Contract Names
Contract Scope
Status
-4.2Km of 700mm diameter pipeline -Acquisition of Land for tank site
-Signed Contract Kshs. 226m
-Physical progress is 40% -Stalled - New procurement
Kenya Towns Sustainable Water Supply and Sanitation Program
Main Contract Names
Contract Scope
Status
Pemba Dam Rehabilitation
Construction of New WTP .Rehabilitation of the Weir Interconnection of the existing system. Improve supply by adding 3000m3 per day to Kwale, Kinango, Likoni and Mombasa via Changamwe.
100%
Changamwe Repooling
-9.8km of sewers -260 Man holes
-25% -Court Injunction by the contractor -Arbitration ongoing
Watamu Water Distribution Network Works
-100% -DLP ongoing
Improvement of Drinking Water and Sanitation Systems in MombasaAFD Projects
Main Contract Names
Contract Scope
Status
Mwache WTP
-Raw water pumping station -186,000 m3/d WTP -Clear Water Tanks
-Bids docs submitted submitted on 10th Jan 23 -Tender Cancelled
NRW Works (MOWASCO)
DMAs Implementation
Procurement of Consultant ongoing at Draft Contract
Likoni Emergency Works
-Works contract singed on 15th August 2021 -Master List tax exemption Approved -Vehicles, pipes and casing specific exemption obtained -52% physical progress/183% of elapsed time
Water and Sanitation Development Project (WSDP)World Bank Projects
Main Contract Names
Contract Scope
Status
Baricho Replacement Boreholes
-Boreholes 1,3 & 4 -Drilling & Equipping -Local Protection Works
-Completed
Mombasa North Mainland Lot 1A
-Water Distribution Network (88 km)
-Contract signed on 23rd March 2021 -90% physical progress/211% of elapsed time
North Mainland Nyali Phase 1
-Water Distribution Network (65 km)
-Contract signed on 23rd March 2021 -90% physical progress/211% of elapsed time
Baricho Protection Works
-Gabion Works -4km of Piling Works -8,950 m2 of Access Road
-Completed and on DLP
Second Baricho Kakuyuni Line
-29 km of 800mm pipeline -5,000 m3 tank at Kakuyuni -3 pump sets & Electromechanical works
Coast Water Works Development Agency
Physical Adresss: Mikindani Street, Off Nkurumah Road, Mombasa
Postal Address: P.O. BOX 90417-80100,Mombasa ,
Telephone: 041-2315230
Bribery and Coruption Reporting Number:0717-777444
Email: info@cwwda.go.ke
Complaints: complaints@cwwda.go.ke